Projects

Wind turbine blade transport from Batangas to the mountains of Laguna

Since September 2026, Infinite Link Logistics Group Inc. (ILLGI) has been transporting wind turbine blades of about 24 t each from a loading and storage yard in Batangas to turbine sites in the mountains of Laguna, Luzon.

Each blade is loaded onto its transport vehicle at the yard in Batangas and moves by night convoy, with police escort, to the shore of Laguna de Bay. The vehicle carrying the blade rolls onto a barge, crosses the lake and rolls off on the far shore. From there the convoy continues to the start of the mountain road, then along a steep, narrow road to the turbine sites.

On the mountain section the blades travel on self-propelled blade lifters. Where trees, roofs and tight bends are in the way, the lifter raises the blade at the angle set by the route survey and transport plan.

The work follows an approved method statement, journey management plan and clearance drawing set, with toolbox talks and journey briefings, and daily progress reports to the client.

Scope
wind turbine blade transport from the loading and storage yard to the turbine sites
Route
Batangas → barge across Laguna de Bay → mountain road → turbine sites in Laguna
Cargo
wind turbine blades, about 24 t and 81 m long each
Equipment recorded on 2 November 2026
3 self-propelled blade lifters, 2 high-horsepower prime movers, 1 boom truck, 4 escort and service vehicles
Progress
6 blades delivered to turbine sites as at 30 October 2026; transport continuing
Safety
zero lost-time injuries recorded as at 2 November 2026 in our blade transport on this project

Our operations staff are seconded from our shareholder Kaitong Logistics, which develops its own blade transfer trailers.